Solar Park

Project location:

North Scotland

Sector/Industry:

Renewable Energy

Project Information:

Our client instructed us to undertake a full Utility Search, for a site covering over 1300 hectares. The client opted for our Standard Turnaround service of 10 working days, but asked for the SP Energy Networks results to be forwarded on receipt.

Due to its remote location, and size, this would be a particularly tricky site to work on.

Solution

The DNO (SP Energy Networks) plans were delivered on receipt – just 45 minutes after the client instructed the works.

This project required many hours to process the number of incoming results, and manual searches required, but our experienced Production team delivered a complete pack of results inside the 10-day turnaround.

Results

Our Stats Search uncovered 400kv transmission lines, Openreach cables and Mobile Phone Masts running within the boundary of the site.

Call us with any questions
01702 615566
Get A Quote

Latest Case Studies

Our Commitment to Social Value

Hilltop SEND School Project location: Rotherham, South Yorkshire Client: The Great Yorkshire Build Sector/Industry: Private, Public & Third Sectors Project Information: A client...

View case study

Renewable Energy

Solar Park Project location: North Scotland Sector/Industry: Renewable Energy Project Information: Our client instructed us to undertake a full Utility Search, for a site covering...

View case study

EV Charging

Electric Vehicle Charging Station Project location: Banbury, Oxfordshire Sector/Industry: Electric Vehicle Charging Network Project Information: Our client was at the planning stage...

View case study